"This proposed service would implement Measure A's sales tax funding to provide a meaningful alternative to sitting in traffic," Redwood City Mayor Elmer Martinez Saballos said when the Port of Redwood City announced its ferry terminal environmental report in September. The Draft Environmental Impact Report came out on September 17, 2026. It is the most detailed public description so far of what a Redwood City ferry would be.
On a careful read, the first version is a weekday rush-hour commuter line. The things that would bring the ferry into ordinary life in town are written as later steps: midday and weekend boats, a shuttle with an actual operator, and the restaurant and hotel on the water. The trail along the water is the one exception.
A Few Boats, at the Edges of the Day
The report describes two routes. One runs to the San Francisco Ferry Terminal in about 61 minutes one way. The other runs to Jack London Square in Oakland in about 71 minutes. San Francisco Bay Ferry would run the service. Fares would go on Clipper, the same card that already works on BART, Caltrain and SamTrans.
At launch, the report plans for 3 to 4 weekday peak-period trips in each direction. Midday, weekend and special-event sailings are described as possible additions "as demand grows." The analysis plans for service to grow by up to 20 percent on weekdays and weekends. Each vessel carries up to 320 passengers. With four trips, that tops out at 1,280 seats each way across the commute window.
That is real capacity for people commuting to downtown San Francisco or Oakland. It is not yet a boat you could catch to the Ferry Building on a Saturday morning or for a mid-afternoon appointment in Oakland. The report doesn't publish a timetable, and the Port hasn't announced a fare.
Why the Final Stretch Is Slow by Design
An hour to San Francisco can sound long for a boat. The report's operating assumptions explain much of the gap. Ferries would cruise at 35 knots on the open Bay and slow to 7 knots inside the Redwood Creek channel. The report says the lower speed protects people in kayaks and other non-motorized craft, along with marine and land species and their habitat.
The terminal's location is the reason. The site is a 9.2-acre Port parcel where Redwood Creek meets Westpoint Slough. Redwood Creek borders it on the west, the slough on the north, Frontage Road and the Union Pacific tracks on the east, and the CEMEX aggregate and cement terminal on the south. Bair Island lies across the creek. To reach open water, every sailing would have to make that slow trip down the creek first, out and back.
The boats themselves come with a caveat. San Francisco Bay Ferry is phasing in zero-emission vessels across its fleet. The report says that change is not yet feasible for longer, more energy-intensive routes like these. It therefore assumes Tier 4 engines running on renewable diesel, and expects zero-emission boats once those vessels reach the end of their 25-year life.
250 Parking Spaces for a 320-Seat Boat
The landside plan matters as much as the boats. The report calls for a 250-space parking lot for ferry riders, a pickup and drop-off area, and "transit stops for shuttle services to the project site that would be established." The lot has fewer spaces than a single boat has seats. If the first schedule ever filled, most riders would need to arrive some other way than parking.
The stops are planned, but the service to use them isn't. The Draft EIR doesn't name a shuttle operator, a SamTrans route or a frequency. This gap has been known for a while. The Port's January 2022 business plan named SamTrans and Commute.org as possible first-mile and last-mile providers. It also noted that neither the Port nor the City had the staff or equipment to run regular shuttle service. For Redwood Shores, the gap is plain to see. The terminal sits across Redwood Creek from Bair Island, but the report doesn't describe any connection from the Shores side.
The bike plan is more concrete. The western leg of Seaport Boulevard, at the entrance to Pacific Shores Center, would be widened for a two-way Class I bike path and a sidewalk, both separated from traffic. The terminal would have at least 16 secure lockers for bikes and scooters, plus short-term racks. That exceeds what the City's Bicycle Parking Design Guidelines recommend for long-term secure parking. Sixteen lockers are a start, set against hundreds of seats.
The Part You Could Use Without a Ticket
Of everything in the plan, the trail would reach the most people who never board a ferry. An existing Bay Trail segment runs along the water in the waterfront park at Pacific Shores Center. It currently ends about 350 feet short of the project site, at a western parking lot and roughly 300 feet of unpaved path that stops at a security fence.
Under the proposal, that unpaved stretch would be paved and extended about 70 feet to the site boundary near the tide gate. From there, a new Bay Trail segment would follow the water's edge to the terminal and connect to the Seaport Boulevard bike path. The fence would be reconfigured so trail users can reach the site while staying out of the Port's restricted industrial areas. The Port's announcement also lists benches, picnic tables and restrooms.
Today the site is graded, hard-packed dirt. Much of its shoreline is armored with broken concrete and riprap. At its northern edge sits the Shell Unloading Wharf, an abandoned cement wharf built in 1962 that runs out into Westpoint Slough. It was used to unload oyster shells dredged from the Bay so they could be processed into cement.
The bigger waterfront change would come later. The Port proposes rezoning the parcel from General Industrial to General Commercial, in line with its 2020 Vision Plan. That would allow a hotel of up to three stories and 180,000 square feet, up to 20,000 square feet of restaurant space and up to 10,000 square feet of offices, all along Westpoint Slough. The Port estimates about 400 new jobs from those uses. The Port also points to an emergency role. It is a FEMA-designated Federal Staging Area for the South Bay, and ferries could carry first responders and supplies in or evacuate people if roads and bridges were out.
The Calendar Between Now and a First Sailing
The Draft EIR lays out construction in sequence, with work estimated to start in 2027:
- Raise the 9.2-acre site to 17 feet NAVD, which takes seven to nine months.
- Build the terminal, parking lot, Bay Trail extension, Seaport Boulevard widening and site access, relocate the railroad track and replace a maintenance building, which takes about 15 months.
- Start the hotel, restaurant and office uses right after the terminal is finished, which takes about 24 months.
The full program comes to about 48 months. Steps one and two alone run roughly two years. So if the 2027 start holds, the terminal itself would be ready around 2029 at the earliest, with the waterfront buildings about two years after that. The Port hasn't published an opening date, so that is an estimate based on the report, not a promise.
Funding is less settled than the schedule. The Port's September 24, 2026 announcement says the project is eligible for up to $15 million in San Mateo County Measure A transportation sales tax funding and would need local matching funds. Redwood City Pulse reported in January 2025 that the project had been put back into the region's long-range Plan Bay Area 2050+, which improves its eligibility for federal ferry grants. That report also gave a cost estimate of about $100 million. That figure is almost two years old, and the 2026 environmental documents don't update it.
Reading It Yourself Before November 2
The Draft EIR lists five areas with significant impacts: air quality, hazards and hazardous materials, biological resources, noise and vibration, and geology, soils and paleontological resources. The proposed mitigation includes Tier 4 construction engines where available, a five-minute limit on nonessential idling, seasonal windows for in-water work, biological monitoring, and shielded, downward-facing lighting so light doesn't spill onto the marsh. For pile driving, the controls favor vibratory methods and require cushioning and monitoring if impact hammers are needed.
The full document is on the Port's ferry project page. Printed copies are at the Port office at 675 Seaport Boulevard, the Downtown Library at 1044 Middlefield Road and the Redwood Shores Branch Library at 399 Marine Parkway. The 45-day comment period ends at 5 p.m. on November 2, 2026. Comments go to project manager Don Snaman, either by email at [email protected] or by mail to the Port's Seaport Boulevard address. A public open house runs from 11 a.m. to 12:30 p.m. on Wednesday, October 7, in the Board of Commissioners meeting room at the Port office. Written comments can also be turned in there.
The comment window is the time to say what the first schedule should include, whether that's a midday boat, a named shuttle or a link from Redwood Shores. The report already describes each of these as something to add later.
If you own near Seaport Boulevard or along the bayfront and wonder what a future ferry terminal might mean for your property, Robert Pedro has followed Redwood City projects like this since 1994 and is glad to talk it through with you. Start with Get My Valuation and we'll go from there.